It rained lightly on and off today, and we were still able to make some progress. PCEC was out again starting at 8:00 am to finish the trench for our electric line. They were also able to get the transformer placed. Pretty soon we'll have power to the site. That's when the fun begins.
In other news, we still have a bit of water in the basement, but its starting to dry out. If my plan works out, we'll finish the basement dig and start the foundation Monday. We also have a bit of green starting to pop up out in the fields.
Daily Stats | Hours Worked |
Cost
| |||
Day | Trevor | Family/Friends | Contractors | ||
Today | 24 | 0 | 0 | 16 | |
All Time | 24 | 21.5 | 20.5 | 98.5 | $13,496.75 |
Summary of 4/30/2014
| Work Done Today | ||||
Underground trench for electric line, placed transformer
| |||||
Materials Used Today | |||||
Who Helped Today | |||||
Contractors On Site | |||||
PCEC
| |||||