Friday, September 19, 2014

Day 166: Back Patio

Friday

Yesterday we got some good weather and some good progress. But first, a quick shot of the front of the house to catch everyone up on where we are:


Now to the back of the house. Our flatwork contractor, Vanderford Construction, was out and put in the back patio. The back patio also has concrete piers underneath it to support the posts that hold up the back deck and the roof overhang. We were looking forward to getting the patio poured so we could finish up the framing.



I opted to bring the concrete around the back of the suspended garage to give myself a concrete pad behind the back double door. It'll be much easier to bring future projects in and out of the back double doors with a mini driveway.





Daily StatsHours Worked
Cost
DayTrevorFamily/FriendsContractors
Today166220
All Time1661101071162.5$13,496.75
Summary of 9/19/2014
Work Done Today
Cleaned up site
Materials Used Today
Who Helped Today
Reed, Emmy, Abby
Contractors On Site