After a nice three-day weekend, it was time to get back to work. Our framing crew was back at it early in the morning and got a good start. They finished up the second story floor, including the bridge between the girls and boys rooms. They also got the east wall up.
After they'd left we went out as a family and did a little clean up. Mandy picked up a burn barrel today and we put it to quick use, burning small scraps here and there. The kids thought it was fun to get to through small boards out the second story window and burn things. Will was in boy heaven. They were thrilled when we all climbed up the ladder and got to stand on the second story floor.
Daily Stats | Hours Worked |
Cost
| |||
Day | Trevor | Family/Friends | Contractors | ||
Today | 149 | 2 | 5 | 50 | |
All Time | 149 | 102 | 102 | 690.5 | $13,496.75 |
Summary of 9/2/2014
| Work Done Today | ||||
Finished second story floor and second story wall peaks
| |||||
Materials Used Today | |||||
SIP package, burn barrel
| |||||
Who Helped Today | |||||
Mandy, Reed, Emmy, Abby, Will
| |||||
Contractors On Site | |||||
Square Cuts
| |||||