We required three steel beams in to support the suspended garage floor. They were 12 inches tall and 26 lbs per linear foot, or W12-26. They were also about 24 ft long, making them about 600 lbs each. Fortunately, the outfit we bought them from, Jones Metal in Kansas City, also places them upon delivery. Thanks to Kim, we have a few shots of them going in:
The beams rest in beam pockets that were formed in the concrete when it was poured. The metal pan for the concrete will go on top of the beams prior to pouring the suspended floor, which should happen this Friday if all goes well.
Daily Stats | Hours Worked |
Cost
| |||
Day | Trevor | Family/Friends | Contractors | ||
Today | 107 | 0 | 0 | 2 | |
All Time | 107 | 98 | 93 | 412.5 | $13,496.75 |
Summary of 7/22/2014
| Work Done Today | ||||
Materials Used Today | |||||
3 beams, W12-26 x 24'
| |||||
Who Helped Today | |||||
Contractors On Site | |||||
Jone's Metal
| |||||