We got our ground rough plumbing in and inspected last week. The next step after that is to get gravel in on top of the plumbing and graded flat to form a firm base for the concrete floors of the basement to go on. Our flatwork guy got his crew out on June 27 and they got the gravel in. It's nice to have a level floor in the house to walk on, albeit a gravel one.
Daily Stats | Hours Worked |
Cost
| |||
Day | Trevor | Family/Friends | Contractors | ||
Today | 82 | 0 | 0 | 8 | |
All Time | 82 | 96 | 93 | 338.5 | $13,496.75 |
Summary of 6/27/2014
| Work Done Today | ||||
Rocked basement
| |||||
Materials Used Today | |||||
Gravel, about 75 tons
| |||||
Who Helped Today | |||||
Contractors On Site | |||||
Vanderford Construction
| |||||