Tuesday, November 18, 2014

Dad 226: Cedar Siding Underway

Tuesday

Over the past week we've had record lows. The high has been below 40 degrees for over ten days, and the low was in single digits this morning. Despite the cold temperatures, I've had a lot of help. Dad and Krishn came up last week and helped last Tuesday through Friday. We worked on the cedar siding on the exterior of the house. We had pre-stained the siding a month or so ago and it was good to finally get around to putting it up.






Saturday, Monday, and today I worked on the PEX plumbing. I installed two manifolds in the basement to which the water supply lines will be attached. I'm using a "home run" system, meaning every water using device (shower, tub, sink, etc) will have it's own pipe running all the way back to the manifold for both hot and cold water. The manifold allows me to turn the water supply to each device on and off independently.





Daily StatsHours Worked
Cost
DayTrevorFamily/FriendsContractors
Today2261030
All Time2264054541420$13,496.75
Summary of 11/18/2014
Work Done Today
PEX install
Materials Used Today
PEX
Who Helped Today
Reed, Emmy, Abby
Contractors On Site